Elmhurst Refurbishment, Bromsgrove School

To increase their offering to students, Bromsgrove School appointed Deeley Construction to carry out the refurbishment of their Elmshurst block.

In addition to proposals to upgrade and enhance the existing board house’s envelope the interior was substantially refurbished with the addition of en-suite bathrooms and alterations made to the communal social space.

The alterations to the landscaped car parking adds 64 spaces and extends the strategy of enhancing the schools grounds with hard and soft landscape improvements.

The main refurbishment package consisted of the reconfiguration of 20 no. dorms to provide 91 no. bed spaces. The works were phased to maintain use of facility during term time. We offered the project team an alternative programme of phasing reducing it from 6 phases to 4, ultimately saving 12 weeks on the overall project programme.

The project also involved some asbestos removal works so we therefore measures were put in place to ensure all subcontractors were DBS checked and had undertaken the Asbestos Awareness Training, regardless of their trades involvement on the project.

£2.3 million
Contract Value

July 2019 - July 2019
Timeframe

JCT SBC with Quanties 2016
Form of Contract

Share